Planned Maintenance Notices
Want to receive these messages directly? Click here to join our mailing list.
Current Notices
Championship Golf Course Closure - October 31, 2024
Location: Championship Golf Course
Estimated Timeframe: Thurs., Oct. 31, 2024
Due to an unforeseen political event in Albuquerque, the UNM Championship Golf Course is currently inaccessible and unable to open for today. We sincerely apologize for this last-minute inconvenience.
Tee Times & Refunds: Our team is actively working to reschedule tee times. Alternatively, we are happy to provide refunds if preferred.
Contact Information: For immediate assistance, please contact us at (505)277-0543. Staff are reaching out individually to all customers with scheduled tee times today to discuss rescheduling or refund options.
Thank you for your patience and understanding.
CCAT: Traffic Control for ADA Ramp Construction, Redondo Dr.
Location: North side of Redondo Dr., near CCAT construction
Estimated Timeframe: Mon., Nov. 4 - Fri., Nov. 8, 2024
Please be advised that construction of an ADA ramp on the north side of Redondo Dr., near the CCAT construction site, will begin next week. A temporary crosswalk will be installed as part of the project. Traffic control measures will be implemented early Monday and remain in place until the ramp and crosswalk striping are completed on Friday. Please plan your route accordingly and exercise caution in this area.
Yale & Central, NE Corner Improvement
Location: NE Corner of Central Ave. & Yale Blvd.
Estimated Timeframe: Mon., Sept. 30 - Mon., Dec. 9, 2024 (10 Weeks)
Type: Landscaping, Pathways, Lighting, & Monument Sign Installation
A construction project is scheduled to begin on Monday, September 30, 2024, at the northeast corner of Central Avenue and Yale Boulevard. The work will include updates to landscaping, pedestrian pathways, lighting, and the installation of a new UNM Monument sign. Construction fencing will be in place throughout the project.
We do not anticipate any traffic lane closures on Central Avenue or Redondo Road. However, a brief, temporary lane closure may occur on Yale Blvd. to accommodate sidewalk work and the installation of the monument sign.
Campus Blvd., near Stanford intersection to Girard intersection
Update
Please be advised that a new traffic pattern will be implemented along Campus Boulevard starting on September 23, 2024, as part of ongoing construction efforts.
Active construction will shift work areas to the outer lanes, moving traffic to the center lanes.
Estimated Timeframe: Wed., August 21 - October 31, 2024
Type: Parking Improvement
Key Information:
- Implementation of back-in angled parking along Campus Blvd.
- Traffic will still be able to pass through the area, but drivers may see a slower pace to provide safety to workers on-site and pedestrians
- Please be aware of pedestrians in the area and proceed with caution
This project will increase campus parking capacity by over 100 spaces, reflecting our ongoing efforts to meet the needs of our growing community while prioritizing safety and accessibility.
Upcoming Residential Parking Lot Construction September - October
Please be aware that construction will soon begin on several parking lot projects in residential parking areas to enhance campus security and improve parking facilities. The details for each project are as follows:
- Redondo Tennis Court (East)
Estimated Construction: September 23, 2024 – October 31, 2024
Once construction is completed, this area will become a PARKMOBILE pay station lot.
- Redondo Village R Lot (West)
Estimated Construction: September 30, 2024 – October 31, 2024
The area will be closed off for construction, but parking access will still be available through Redondo Drive. - Coronado/Oñate R Lot (East)
Estimated Construction: October 3, 2024 – October 31, 2024
A portion of the R Lot behind Coronado Hall will be temporarily unavailable due to ongoing construction. Vehicular traffic on Girard Boulevard will not be affected, but the bike lane on Girard will be closed during this period. Parking access will remain available via Girard Boulevard. - Central & Girard R/E Lot (South)
Estimated Construction: One day of work, to be determined soon with advanced notice to campus.
Parking spaces will be blocked off for one day for the installation of bumpers and striping. Further details regarding the closure will be provided soon. - Alvarado R Lot (North)
Estimated Construction: Scheduled weekend in October
The north portion of the Alvarado Hall R parking lot will be closed during a designated weekend in October. Further details regarding the closure will be provided soon.
We appreciate your patience and understanding as we work to enhance the safety and functionality of our parking facilities. Further updates will be provided as needed. Alternative parking arrangements for impacted customers will be provided by UNM PATS.
For more information on how this initiative fits into our broader efforts to enhance campus infrastructure, please visit the Integrated Campus Plan or tune in to the recording from the PATS Town Hall from June 2024, at the time marked 34:14.
Stay updated with UNM PATS on Facebook, X (@UNMPATS), or Instagram (@unm_pats) for advisories, construction notices, permit purchase dates, and more exciting updates. For questions, please call us at 505-277-1938, send an email to parktran@unm.edu, or visit us in person at the PATS Business Office (located in the Cornell Parking Structure). PATS Parking Service Representatives are available to assist Monday through Friday, 7:30 a.m. to 5 p.m.
Past Notices
R Parking Lot (Near Redondo Village) & North Golf Course
Estimated Timeframe: Wednesday, 03/26/24 – Saturday, 03/27/24
Type: Utility Work
Please be aware that there will be utility work conducted in the R parking lot (near Redondo Village) starting Tuesday, March 26. The work will involve conducting hydrothermal drilling/testing and may cause some damage to the ground. Utility work will involve a 30-foot tall drill rig, a water truck, and a mud truck. The areas will be fenced off with signs. Work is starting Tuesday and is expected to last a few days.
R Parking Lot: PATS is working to relocate cars in the impacted area. The area will be fenced off.
North Golf Course: Utility work has concluded on the North Course
Updates
We regret to inform you that our contractors have encountered an equipment breakdown while working at the "R" Parking lot near Redondo Village. As a result, the fencing and equipment will remain in place until repairs are complete, and the project can be finished. Estimated completion is Thursday, April 4. Following initial project completion, the last four fence panels will remain on site until testing is completed, utilizing one parking space. Once complete, the asphalt will be replaced, and the fencing will be removed.
UNM North Golf Course
Estimated Timeframe: Monday, 3/25/24 – Wednesday, 03/27/24
Type: Utility Work
Please be aware that there will be utility work conducted on the North Golf Course starting early next week. The work will involve conducting hydrothermal drilling/testing and may cause some damage to the testing site. Utility work will involve a 30-foot-tall drill rig, a water truck, and a mud truck. The areas will be fenced off with signs. Work is starting Monday and is expected to last 2-3 days.
North Golf Course: Although the utility work is far away from residential buildings on the extended, Northeast edge of the North Golf Course, there may be some inconvenience to normal operations on the course. We are working to minimize any potential damage and plan to restore the area to its previous condition once the work is complete.
Intersection of Tucker and G Parking Lot
Estimated Timeframe: Wednesday, 04/24/24
Type: Stop Sign Installation at the Intersection of Tucker and G Parking Lot
We would like to notify you of forthcoming changes at the intersection of Tucker and G parking lot starting April 24th. Permanent stop signs will be installed, one for eastbound and one for westbound traffic, effectively establishing a four-way stop at this location.
Please be advised that this installation may temporarily impact traffic flow in the area. We appreciate your understanding as we work to enhance safety at this intersection.
UNM North Golf Course
Estimated Timeframe: Monday, 04/08/24 – Friday, 04/26/24
Type: Cleanup
Please be aware that there will be cleanup work conducted on the North Golf Course starting Monday, April 8. The work will involve debris removal including large tree debris, parking posts, and concrete remnants. The area will then be leveled for drainage protection. The areas are fenced off from the golf course and construction signage and cones will be set up before work begins.
Although the work is far away from residential buildings on the extended, Northwest edge of the North Golf Course, there may be some inconvenience to normal operations on the course. We are looking to get more funding for a future project that includes permanent fencing of the area to prevent future dumping in the area.
Redondo Drive Parking Spaces & Centennial Engineering Center
Estimated Timeframe: Wednesday, 04/17/24 – Thursday, 05/14/24
Type: HVAC Replacement
We would like to inform you about an upcoming HVAC replacement estimated for Wednesday, April 17. The work will involve cranes on-site and will create increased noise in the surrounding areas. This replacement will necessitate temporary changes in the vicinity of Redondo Drive and the Centennial Engineering Center, as outlined below:
April 18 some parking spaces along Redondo will be blocked off to facilitate the plans. PATS is working to relocate cars in the impacted area. Once the crane is on-site and set up, our presence will primarily be concentrated within the designated work area. The delivery truck and crane work should be complete by the end of the day, April 18. On Thursday, April 18 there will be increased noise levels on the north side of Centennial Engineering Center.
Updates
The HVAC replacement project, initially scheduled for April 16th with delivery and crane setup planned between the Ford Building and Centennial Engineering, has been rescheduled to May 9, from 6:00 a.m.–3:30 p.m., due to logistical adjustments. During this period, temporary restrictions will be in place in the alley between the Ford Utilities Building and the Centennial Engineering Building. Additionally, four parking spots across from the double gates into the alley between Ford and Centennial on Redondo will be closed to facilitate crane and semi-trailer movement. However, unforeseen circumstances, including winds and crane availability issues, have necessitated pushing back the project completion date to the end of the day on May 14. Fortunately, the units are now on site, eliminating the need for the parking spaces on Redondo. Going forward, all remaining work until May 14 will be conducted in the alley between the Centennial Engineering Building and the Ford Utility Building.
East of Scholes Hall
Estimated Timeframe: Late June 2024
Type: Tree Removal
Over the years, Facilities Management has been actively managing several defects on the large cottonwood tree located just east of Scholes Hall. Unfortunately, a recent limb failure has necessitated the immediate removal of the entire tree due to safety concerns. The removal process has already begun, but will take several days to complete. Our priority is to ensure safety, particularly over the weekend. We plan to remove enough of the canopy to mitigate any immediate risks, and barricades will be placed accordingly.
Girard R Lots
Estimated Timeframe: Tues., July 16 - Tues., August 27, 2024
Redondo Tennis Court (East)
Estimated Timeframe: Tues., July 16 - Mon., September 30, 2024
Type: Parking Lot Construction
UNM Parking & Transportation Services (UNM PATS) would like to inform our community effective Tuesday, July 16 construction projects will restrict parking in certain lots.
For further information, please contact the PATS team, or view the Town Hall recording, time marked at 25:45.
West of Scholes Hall, Sidewalk / Green Area
Estimated Timeframe: Tues., July 16 - Wed., July 17, 2024
Type: Tree Removal
The large cottonwood tree west of Scholes Hall was recently evaluated and found to have advanced decay in one of its limbs, compromising the tree's stability. As a result, the primary maintenance work to remove the tree is scheduled to begin on Tuesday, July 16. Note, two young Bur Oaks were previously planted nearby to eventually replace this tree. Additional maintenance is expected to follow to remove the tree stump. For further information, please contact the Facilities Management team.
North of Scholes Hall, Buena Vista Reserved Parking
Estimated Timeframe: Mon., July 1 - Fri., July 5, 2024
Type: Roof Maintenence on Dane Smith Hall
Starting Monday July 1, the reserved spaces North of Scholes Hall on Buena Vista Rd. will be closed due to maintenance on the roof of Dane Smith Hall. To accommodate parking during this time, temporary reserved parking spaces in the C lot are available. There is a possibility the work could be extended to July 9th.
Campuswide
Estimated Timeframe: August 29, 2024
Type: Power Outage
Power was temporarily down across campus. Utility Services acted quickly to restore power, additional details may become available as information is released.
Lobo Welcome Center / Jonson Gallery
Estimated Timeframe: Saturday, September 7, 6 a.m. - 4 p.m.
Type: Planned Power Outage
Please be advised that a planned power outage is scheduled for Saturday, September 7th at the Lobo Welcome Center and Jonson Gallery. This outage is necessary to support repair efforts by UNM Utility Services. We apologize for any inconvenience this may cause and appreciate your understanding.
Yale & Tucker Intersection Closure
Estimated Timeframe: Sat., Oct. 5 - Sun., Oct. 6, 2024 (2 Days)
Type: Roadway Construction
Please be advised that construction work at the Yale & Tucker intersection is scheduled to begin over the weekend of 10/5-6. This project will reduce the intersection to one lane as part of ongoing work around the Children’s Psychiatric Center Inpatient Building. Two-way traffic will be maintained, with workers directing traffic flow.
The roadway will be returned to full service by Monday, October 7.
Click here to view the barricade plan.
Kiva Stairway
Estimated Timeframe: Mon., Sept. 16 - Mon., Oct. 7 (3 Weeks)
Type: Exterior Staircase Maintenance
Please be aware that maintenance work on the Kiva stairs is scheduled to begin soon. The project will involve replacing the handrails and concrete, while maintaining the current design and layout of the stairs. The handicap ramp will remain unaffected and fully accessible throughout the project.
The area around the Kiva stairs will be fenced off during this period; however, this work will not impact access to Mesa Vista Hall.
CCAT Construction & Parking Relocations
UNM Parking & Transportation Services (UNM PATS) would like to inform A-lot & R-lot permit holders and the UNM community effective Monday, October 14 construction projects will restrict parking in certain lots. In preparation of, the Center for Collaborative Arts & Technology (CCAT) construction, PATS is making several adjustments to our parking solutions. Here is what you need to know:
AFFECTED PARKING LOTS:
- R/E-Lot near Central Avenue and Girard Boulevard
- Will be designated as an A/E-lot
- Will be designated as an A/E-lot
- A-Lot will be permanently closed due to construction as of Monday, 10/14/2024
Complete Closure of Tucker Lane Near Children’s Psychiatric Center (CPC)
Update
Tucker Lane is currently open for traffic. Tucker Ln. will have a scheduled closure on Monday 10/21 from 10 A.M. - 3 P.M. to support the concrete replacement of the sidewalk, curb, and gutter.
Future complete closure will occur for asphalt at a later scheduled date.
Location: Tucker Lane between Yale & Camino de Salud
Estimated Timeframe: Friday, October 18
Type: Emergency Water Line Repair
Please be advised that Tucker Lane near the UNMH Children’s Psychiatric Center (CPC) is now completely closed due to an emergency water line repair. Safety barricades and signage are in place, and the closure will remain until the issue is resolved. UNMH Planning and Construction is actively working to restore normal operations.
Expect shuttle delays this morning (10/18) due to this closure, along with ongoing construction at the Lomas and University intersection.
Closure of Tucker Lane Near Children’s Psychiatric Center (CPC)
Location: Tucker Lane between Yale & Camino de Salud
Estimated Timeframe: Friday, October 25, 10 A.M - 3 P.M.
Type: Asphalt Work
Please be advised that Tucker Lane near the UNMH Children’s Psychiatric Center (CPC) will be closed due to new asphalt from the earlier water line repair.
Expect shuttle delays (10/25) due to this closure, along with ongoing construction at the Lomas and University intersection.