Planned Maintenance Notices

Current Notices

Location: West of Scholes Hall, Sidewalk / Green Area

Estimated Timeframe: Tues., July 16 - Wed., July 17, 2024

Type: Tree Removal

The large cottonwood tree west of Scholes Hall was recently evaluated and found to have advanced decay in one of its limbs, compromising the tree's stability. As a result, the primary maintenance work to remove the tree is scheduled to begin on Tuesday, July 16. Note, two young Bur Oaks were previously planted nearby to eventually replace this tree. Additional maintenance is expected to follow to remove the tree stump. For further information, please contact the Facilities Management team.

Click here to view map.

  

Past Notices 

Location: R Parking Lot (Near Redondo Village) & North Golf Course

Estimated Timeframe: Wednesday, 03/26/24 – Saturday, 03/27/24

Type: Utility Work

Please be aware that there will be utility work conducted in the R parking lot (near Redondo Village) starting Tuesday, March 26. The work will involve conducting hydrothermal drilling/testing and may cause some damage to the ground. Utility work will involve a 30-foot tall drill rig, a water truck, and a mud truck. The areas will be fenced off with signs. Work is starting Tuesday and is expected to last a few days.

R Parking Lot: PATS is working to relocate cars in the impacted area. The area will be fenced off. 

North Golf Course: Utility work has concluded on the North Course

Click here to view map.

Updates

We regret to inform you that our contractors have encountered an equipment breakdown while working at the "R" Parking lot near Redondo Village. As a result, the fencing and equipment will remain in place until repairs are complete, and the project can be finished. Estimated completion is Thursday, April 4. Following initial project completion, the last four fence panels will remain on site until testing is completed, utilizing one parking space. Once complete, the asphalt will be replaced, and the fencing will be removed.

Location: UNM North Golf Course

Estimated Timeframe: Monday, 3/25/24  – Wednesday, 03/27/24

Type: Utility Work

Please be aware that there will be utility work conducted on the North Golf Course starting early next week. The work will involve conducting hydrothermal drilling/testing and may cause some damage to the testing site. Utility work will involve a 30-foot-tall drill rig, a water truck, and a mud truck. The areas will be fenced off with signs. Work is starting Monday and is expected to last 2-3 days.

North Golf Course: Although the utility work is far away from residential buildings on the extended, Northeast edge of the North Golf Course, there may be some inconvenience to normal operations on the course. We are working to minimize any potential damage and plan to restore the area to its previous condition once the work is complete.

Click here to view map.

Location: The intersection of Tucker and G Parking Lot

Estimated Timeframe: Wednesday, 04/24/24 

Type: Stop Sign Installation at the Intersection of Tucker and G Parking Lot

We would like to notify you of forthcoming changes at the intersection of Tucker and G parking lot starting April 24th. Permanent stop signs will be installed, one for eastbound and one for westbound traffic, effectively establishing a four-way stop at this location.

Please be advised that this installation may temporarily impact traffic flow in the area. We appreciate your understanding as we work to enhance safety at this intersection.

Click here to view map.

Location: UNM North Golf Course

Estimated Timeframe: Monday, 04/08/24 – Friday, 04/26/24

Type: Cleanup

Please be aware that there will be cleanup work conducted on the North Golf Course starting Monday, April 8. The work will involve debris removal including large tree debris, parking posts, and concrete remnants. The area will then be leveled for drainage protection. The areas are fenced off from the golf course and construction signage and cones will be set up before work begins.

Although the work is far away from residential buildings on the extended, Northwest edge of the North Golf Course, there may be some inconvenience to normal operations on the course. We are looking to get more funding for a future project that includes permanent fencing of the area to prevent future dumping in the area.

Click here to view map.

Location: Redondo Drive Parking Spaces & Centennial Engineering Center

Estimated Timeframe: Wednesday, 04/17/24 – Thursday, 05/14/24

Type: HVAC Replacement

We would like to inform you about an upcoming HVAC replacement estimated for Wednesday, April 17. The work will involve cranes on-site and will create increased noise in the surrounding areas. This replacement will necessitate temporary changes in the vicinity of Redondo Drive and the Centennial Engineering Center, as outlined below:

April 18 some parking spaces along Redondo will be blocked off to facilitate the plans. PATS is working to relocate cars in the impacted area. Once the crane is on-site and set up, our presence will primarily be concentrated within the designated work area. The delivery truck and crane work should be complete by the end of the day, April 18. On Thursday, April 18 there will be increased noise levels on the north side of Centennial Engineering Center.

Click here to view map.

Updates

The HVAC replacement project, initially scheduled for April 16th with delivery and crane setup planned between the Ford Building and Centennial Engineering, has been rescheduled to May 9, from 6:00 a.m.–3:30 p.m., due to logistical adjustments. During this period, temporary restrictions will be in place in the alley between the Ford Utilities Building and the Centennial Engineering Building. Additionally, four parking spots across from the double gates into the alley between Ford and Centennial on Redondo will be closed to facilitate crane and semi-trailer movement. However, unforeseen circumstances, including winds and crane availability issues, have necessitated pushing back the project completion date to the end of the day on May 14. Fortunately, the units are now on site, eliminating the need for the parking spaces on Redondo. Going forward, all remaining work until May 14 will be conducted in the alley between the Centennial Engineering Building and the Ford Utility Building.

Location: East of Scholes Hall

Estimated Timeframe: Late June 2024

Type: Tree Removal

Over the years, Facilities Management has been actively managing several defects on the large cottonwood tree located just east of Scholes Hall. Unfortunately, a recent limb failure has necessitated the immediate removal of the entire tree due to safety concerns. The removal process has already begun, but will take several days to complete. Our priority is to ensure safety, particularly over the weekend. We plan to remove enough of the canopy to mitigate any immediate risks, and barricades will be placed accordingly.

Click here to view map.

Location: North of Scholes Hall, Buena Vista Reserved Parking

Estimated Timeframe: Mon., July 1 - Fri., July 5, 2024

Type: Roof Maintenence on Dane Smith Hall

Starting Monday July 1, the reserved spaces North of Scholes Hall on Buena Vista Rd. will be closed due to maintenance on the roof of Dane Smith Hall. To accommodate parking during this time, temporary reserved parking spaces in the C lot are available. There is a possibility the work could be extended to July 9th.

Click here to view map.