Planned Maintenance Notices

planned-maintenance-graphic

Current Notices

Location: The intersection of Tucker and G Parking Lot

Estimated Timeframe: Wednesday, 04/24/24 

Type: Stop Sign Installation at the Intersection of Tucker and G Parking Lot

We would like to notify you of forthcoming changes at the intersection of Tucker and G parking lot starting April 24th. Permanent stop signs will be installed, one for eastbound and one for westbound traffic, effectively establishing a four-way stop at this location.

Please be advised that this installation may temporarily impact traffic flow in the area. We appreciate your understanding as we work to enhance safety at this intersection.

Click here to view map.

Location: Redondo Drive Parking Spaces & Centennial Engineering Center

Estimated Timeframe: Wednesday, 04/17/24 – Thursday, 05/09/24

Type: HVAC Replacement

We would like to inform you about an upcoming HVAC replacement estimated for Wednesday, April 17. The work will involve cranes on-site and will create increased noise in the surrounding areas. This replacement will necessitate temporary changes in the vicinity of Redondo Drive and the Centennial Engineering Center, as outlined below:

April 18 some parking spaces along Redondo will be blocked off to facilitate the plans. PATS is working to relocate cars in the impacted area. Once the crane is on-site and set up, our presence will primarily be concentrated within the designated work area. The delivery truck and crane work should be complete by the end of the day, April 18. On Thursday, April 18 there will be increased noise levels on the north side of Centennial Engineering Center.

Click here to view map.

Updates

The HVAC replacement, originally planned for April 16, delivery and crane setup between Ford Building and Centennial Engineering has been rescheduled to May 9, between 6:00 a.m–3:30 p.m., due to logistical adjustments. Please note that during this time, there will be temporary restrictions in the alley between Ford Utilities Building and Centennial Engineering Building, as well as the closure of four parking spots across from the double gates into the alley between Ford and Centennial on Redondo to facilitate the backing of the crane and semi-trailer into the alley.

Location: UNM North Golf Course

Estimated Timeframe: Monday, 04/08/24 – Friday, 04/26/24

Type: Cleanup

Project Manager: Cinthia Tena, (505)544-6770

Please be aware that there will be cleanup work conducted on the North Golf Course starting Monday, April 8. The work will involve debris removal including large tree debris, parking posts, and concrete remnants. The area will then be leveled for drainage protection. The areas are fenced off from the golf course and construction signage and cones will be set up before work begins.

Although the work is far away from residential buildings on the extended, Northwest edge of the North Golf Course, there may be some inconvenience to normal operations on the course. We are looking to get more funding for a future project that includes permanent fencing of the area to prevent future dumping in the area.

Click here to view map.

Past Notices 

2024

Location: R Parking Lot (Near Redondo Village) & North Golf Course

Estimated Timeframe: Wednesday, 03/26/24 – Saturday, 03/27/24

Type: Utility Work

Please be aware that there will be utility work conducted in the R parking lot (near Redondo Village) starting Tuesday, March 26. The work will involve conducting hydrothermal drilling/testing and may cause some damage to the ground. Utility work will involve a 30-foot tall drill rig, a water truck, and a mud truck. The areas will be fenced off with signs. Work is starting Tuesday and is expected to last a few days.

R Parking Lot: PATS is working to relocate cars in the impacted area. The area will be fenced off. 

North Golf Course: Utility work has concluded on the North Course

Click here to view map.

Updates

We regret to inform you that our contractors have encountered an equipment breakdown while working at the "R" Parking lot near Redondo Village. As a result, the fencing and equipment will remain in place until repairs are complete, and the project can be finished. Estimated completion is Thursday, April 4. Following initial project completion, the last four fence panels will remain on site until testing is completed, utilizing one parking space. Once complete, the asphalt will be replaced, and the fencing will be removed.

Location: UNM North Golf Course

Estimated Timeframe: Monday, 3/25/24  – Wednesday, 03/27/24

Type: Utility Work

Please be aware that there will be utility work conducted on the North Golf Course starting early next week. The work will involve conducting hydrothermal drilling/testing and may cause some damage to the testing site. Utility work will involve a 30-foot-tall drill rig, a water truck, and a mud truck. The areas will be fenced off with signs. Work is starting Monday and is expected to last 2-3 days.

North Golf Course: Although the utility work is far away from residential buildings on the extended, Northeast edge of the North Golf Course, there may be some inconvenience to normal operations on the course. We are working to minimize any potential damage and plan to restore the area to its previous condition once the work is complete.

Click here to view map.